If you've searched for a house extension in Chorley, you're probably trying to work out whether extending beats moving, and what it will actually cost once the scaffolding goes up. Prices across Lancashire vary a fair bit depending on size, ground conditions and how far you push the spec. This guide sets out realistic cost ranges and the local factors that move a quote up or down.
Costs in Lancashire tend to sit a little below the national average, but there is still a wide range depending on what you are building and the finish you want. As a rough guide for a solid, builder-grade finish, not including kitchen units, bathroom fittings or furniture, expect the following.
These figures assume straightforward ground conditions and a standard brick or render finish. Add large glazing, underfloor heating or a vaulted ceiling with exposed steel, and you can easily add 15 to 25 percent onto the base figure.
Several things move the price beyond the size of the room. Lancashire's terrain plays a bigger part than people expect. Plots on the edges of Burnley, Pendle and parts of the Ribble Valley often slope, which means more groundwork, retaining walls or extra foundation depth before a single brick goes up.
Get at least three quotes and ask each builder to break the price down by groundwork, structure, roof, and first and second fix, so you can compare like for like rather than just a bottom line figure.
Many single storey rear extensions fall under permitted development, meaning you can build without a full planning application if you stay within government size and height limits. That said, Chorley, Burnley and Pendle councils all have conservation areas, including parts around Astley Park and Euxton in Chorley, and sections of Burnley and Clitheroe, where permitted development rights are restricted and a full application is needed regardless of size.
Whichever route you take, the work still has to meet Building Regulations, covering structural calculations, insulation levels and fire safety. This is separate from planning permission and gets signed off during and after the build.
A single storey rear extension typically takes 10 to 14 weeks once the diggers arrive, assuming reasonable weather and no surprises underground. Double storey and wrap-around jobs usually run to 4 to 6 months, as there is more roof, more structural work, and often a kitchen refit layered on top.
Build in a contingency of 10 to 15 percent of the total budget for anything unexpected, such as old drains, poor ground or a damp issue uncovered once work starts. Most established Lancashire builders work to staged payments tied to progress rather than asking for large sums upfront, which is worth checking before you sign anything.
A house extension involves several trades working in the right order: groundwork, bricklaying, roofing, electrics, plumbing and plastering. It is worth choosing a builder who manages this directly rather than subcontracting every stage and hoping it joins up. A firm based locally, used to building on Lancashire's sloping sites and matching the stone and brick common across Burnley, Chorley and Pendle, will usually give you a more realistic quote and fewer surprises once work starts.